Sewer to go on-line by this fall

By By Thomas Tingle
Record Managing Editor
Construction of a new wastewater treatment facility for the city of Madison will be completed this fall. However, construction of the city's new water treatment plant has been delayed by seven months.
According to Whitey Bressette, general manager for the Water and Wastewater Department, the $23 million wastewater treatment facility, which is located off Landers Circle, is due to go on-line by the end of September or the first of October. Bressette said construction of the facility began a year ago. Upon its completion, the city of Madison will no longer rely on the city of Huntsville to treat its wastewater.
"We will be able to treat six thousand gallons of water per day at the new facility and it has been designed for future expansion," Bressette said.
Construction of a new water treatment plant for the city has been delayed by seven months due to funding regulation changes.
Bressette said the plant is scheduled to go on-line in July 2003. Funding to build the plant – budgeted at $8 million – will come through the State Water Revolving Fund.
"Due to funding regulation changes, we've had to delay the construction of the new plant and that has been done to save on interest costs," Bressette said.
Upon its completion, the plant will be able to treat eight thousand gallons of water per day with up to 12 thousand gallons of water per day treatable.
"At this time, the location of the water treatment plant is set to be built on property that now belongs to Intergraph near the rock quarry," Bressette said. "That is under negotiation at this time. If the roads are not dedicated to the city of Madison, we will have to look at another location to build the plant. We are looking for additional property as a back-up plan."
Bressette said between four to five acres of property is needed to build the plant and it will take a year to build the facility once construction begins.

Madison

American Legion to honor Gold Star families on Memorial Day

James Clemens High School

Dr. Kerry Donaldson honored as ‘Alabama PTA Principal of the Year’

Bob Jones High School

Bob Jones Jazz Band to play at Jazz Brunch at Madison Senior Center

Harvest

Madison Lions’ air filtration helps Village of Promise, Second Mile

James Clemens High School

Jets audio/visual students ace state, head to nationals

James Clemens High School

James Clemens, Liberty reach finals in Science Bowl

Bob Jones High School

City Rivalry Like Never Before: Baseball Playoffs- Bob Jones vs. James Clemens- A “Hatfields and the McCoys” Local Battle

Madison

Barons best Trash Pandas in pitchers’ duel

Madison

Patriots set the stage for rematch with Jets in Final Four

Madison

Jets soar into semis with Hoover sweep, Pats next

Events

Bless Fest returns for second year of spring family fun this weekend

Events

Local students organize MadFest for day of fun, service

Madison

Bob Jones bests Thompson in Game 1 of playoff tilt

Bob Jones High School

Fourth-graders absorb ‘The History of Madison’ from Cindi Sanderson

Harvest

VIP to host Charity Golf Tournament on Redstone Arsenal

Harvest

AUSA sponsors ‘Operation Eagle Claw’ about freeing hostages in Iran

Madison

MVP’s plant giveaway to celebrate Monarch mural outside Honest Coffee

Harvest

The Madison Village celebrates its 25th anniversary

Bob Jones High School

Optimist Club grants boost service options to youth

Digital Version

Digital version of The Madison Record – May 1, 2024

Bob Jones High School

Bob Jones sweeps Sparkman to advance in playoffs

Digital Version

Digital version of The Madison Record – April 24, 2024

Madison

I-565 nighttime detours planned for Exit 10 work in Madison

Madison

Liberty Middle School student passes away after medical emergency on campus

x