Bressette not happy about paying to move water line

By Staff
Mitch Freeman Madison County Record
Madison Water and Wastewater workers will have to relocate a water line because of a Huntsville road project and the water board is not happy about having to pay for it.
Whitey Bressette, water and wastewater board general manager, said that a 2,200-foot water line on Slaughter Road, near Ferrel Drive, is going to have to be moved to accommodate a Slaughter Road widening project.
He said the labor and materials involved would cost around $50,000. The work is expected to take 10-15 days.
Bressette said the question of who will have to pay for moving the water line has not been answered and that the issue is being researched.
"We weren't given enough time to plan and budget," Bressette said.
"We wouldn't have incurred these costs if they weren't widening the road," board member Larry Helms said.
Board member Larry Vannoy said that the city of Madison had to pay to move gas lines when County Line Road was widened. He said that he didn't understand the difference and that Huntsville should pay for moving the water line.
Bressette said that the old cast iron pipe could not be left under the widened road. He said if there were ever a problem with the water line, the city would be responsible for digging through the road and repairing it.
In other business, a project that includes moving the water line that runs along the southern end of County Line Road was approved. According to Bressette, this project has been planned and budgeted for sometime and is being done in conjunction with converting the two-lane portion of the County Line Road to four lanes.
Some 930 feet of 12-inch water line will replace existing pipe from the railroad tracks that pass under the road to Madison Blvd., where new water line will be installed, running east along Madison Blvd. to Putman Industrial Park. The project is about to get underway and is expected to cost $166,300, according to Bressette.
Construction of a new water treatment plant can now move forward as a result of approval of agreement details with the city of Madison. The plant will be built at Rock Quarry, east of Intergraph.
According to Bressette, the Quarry Water Treatment Plant will have the ability to process up to 8,000,000 gallons of water per minute. Water will come from nearby wells and flow into a raw water tank, which is also part of the project.
Bressette said the new plant will eliminate the Drake plant near Lady Ann Lake, off of Zierdt Road. Along with the Quarry plant, the Keene Water Treatment Plant on Gillespie Road will supply Madison's water needs for the next 10 years, Bressette said. The Keene plant can process up to 6,000,000 gallons of water minute.
Bressette reported to the board that the Madison Growth Commission continues to ask for water and sewage lines in the Burgreen Road area, running north to Highway 72. Bressette said they would have to wrap the lines around a large low-lying area behind the Limestone Flea Market and that it is cost prohibitive to do so.
"Nothing has changed," Bressette said. "We are fully committed to existing plans and budget until 2008."
Vannoy got a positive answer for a request he brought to the board from volunteers who are building a second concession stand at Palmer Park A sewage line will be extended to support the new concession stand next spring, according to board field staff.

Madison

Barons best Trash Pandas in pitchers’ duel

Madison

Patriots set the stage for rematch with Jets in Final Four

Madison

Jets soar into semis with Hoover sweep, Pats next

Events

Bless Fest returns for second year of spring family fun this weekend

Events

Local students organize MadFest for day of fun, service

Madison

Bob Jones bests Thompson in Game 1 of playoff tilt

Bob Jones High School

Fourth-graders absorb ‘The History of Madison’ from Cindi Sanderson

Harvest

VIP to host Charity Golf Tournament on Redstone Arsenal

Harvest

AUSA sponsors ‘Operation Eagle Claw’ about freeing hostages in Iran

Madison

MVP’s plant giveaway to celebrate Monarch mural outside Honest Coffee

Harvest

The Madison Village celebrates its 25th anniversary

Bob Jones High School

Optimist Club grants boost service options to youth

Digital Version

Digital version of The Madison Record – May 1, 2024

Bob Jones High School

Bob Jones sweeps Sparkman to advance in playoffs

Digital Version

Digital version of The Madison Record – April 24, 2024

Madison

I-565 nighttime detours planned for Exit 10 work in Madison

Madison

Liberty Middle School student passes away after medical emergency on campus

Huntsville

Lexi Regensburger promotes HEALS for Girl Scout Gold

Harvest

Rocket City Novas, a new dance krewe, sashay into town

Harvest

Asbury Car & Bike Show to feature vehicles in pristine condition

Liberty Middle School

Liberty takes first-place finish in State MathCounts

Harvest

Fantasy Playhouse to launch ‘Space Monkeys!’ on May 9-12

Harvest

Defense Innovation Summit to explore tech in national security

Madison

‘Sounds of Summer’ concerts return to Home Place Park

x